Commissioning of Instruments

 

Instrument Commissioning
Echidna commenced
Wombat commenced
Kowari commenced
Koala commenced, but repair required
Platypus start in July
Quokka start in July
Taipan start in August

After the commissioning phase all instruments will have friendly-user experiments before being officially scheduled. However, an operating license (for each instrument) is required for scheduling any user experiments.