Learn about ANSTO's core activities; the OPAL research reactor, its science, safety culture, board and organisational structure, news visitors information and events.
Regulatory Disclosures: 2010
The matters listed on this page cover safety-related incidents that occurred during 2010 which were either a regulatory licence breach or were regarded as significant to ANSTO and our employees. For the most current year's list, please see our main Regulatory disclosures page, or you can find earlier radiological incidents that arose between 2000 and 2009.
Find more details on the regulations governing ANSTO.
| 27 Dec 2010 | An overhead light was found to have dropped from the ceiling over an entrance to a building due to a faulty safety lanyard. No one was injured by the falling light. Other light fittings have been inspected. | Notified to Comcare |
| 20 Dec 2010 | A strip-heater overturned causing wall panelling to smoulder. Area evacuated and emergency response personnel called when smoke noticed by nearby staff. No personnel injury occurred and property damage confined to wall panelling near heater. | Notified to Comcare |
| 10 Dec 2010 | An ANSTO staff member experienced nausea, headache and confusion after working on an instrument in a cave entrance at a remote monitoring site. Work was immediately stopped and symptoms disappeared by the following day. Symptoms most likely to have resulted from factors apart from air quality. Procedures for environmental field work have been reviewed and updated.
| Notified to Comcare |
| 1 Dec 2010 | A contractor cut through an insulated electrical cable, activating the protective circuit breaker and the gas detection system in the area. No persons were injured in this event. Equipment being used was double insulated and protected by a residual current device. All equipment is correctly tagged and within the required dates. Electrical safety procedures will be reviewed and updated and staff reminded of requirements. | Notified to Comcare |
| 19 Nov 2010 | contractor received a mild electric shock when they came into contact with the metal work of the false ceiling support grid. The electrical supply was isolated, and the source of the fault was found to be a damaged power cord adjacent to the fitting that had come into contact with the false ceiling support metalwork. No injury was received from the shock. | Notified to Comcare |
| 15 Nov 2010 | Contractors were found to be working in a restricted area where asbestos had previously been identified in floor trenches. The contractors did not access the trenches. The area that was accessed by the contractors was assessed by an accredited laboratory and no asbestos material was identified. Asbestos Management Plan reviewed and updated. Staff reminded of these requirements. | Notified to Comcare |
| 1 Nov 2010 | CT-scanners used for imaging of small animals in clinical trials identified as being unlicensed during ARPANSA inspection. No safety consequences as correct radiation protection measures were being used. | Notified to ARPANSA |
| 29 Oct 2010 | A coupling between a pump motor and flywheel failed and debris penetrated the equipment guard during testing of the pump. Work immediately stopped and pump electrically isolated. No injuries were sustained.
| Notified to Comcare |
| 18 Oct 2010 | Ion exchange column and water seal removed from storage block for maintenance and dose optimisation in the de-fuelled HIFAR facility. The removal of these minor componets technically required approval from ARPANSA. There were no safety consequences as correct radiation protection measures were used.
| Notified to ARPANSA |
| 1 Oct 2010 | The start-up battery for a generator failed when manual start-up attempted during routine maintenance due to high ambient temperature. No injuries were sustained. Battery replaced with one using temperature compensation and inspection checklist reviewed and updated. | Notified to Comcare |
| 21 Sept 2010 | Guttering collapsed underneath a boom lift whilst being driven over a kerb. No injuries or damage to boom lift sustained. Guttering repaired to good condition. | Notified to Comcare |
| 13 Aug 2010 | Two low activity sources identified as missing from Activity Standards Laboratory as part of internally-initiated management review. Reported to ARPANSA immediately and comprehensive remediation plan initiated. No radiological consequences identified from loss of sources.
| Notified to ARPANSA |
| 16 July 2010 | Level in diethyl ether distillation rig being used in a laboratory experiment was noticed to be low. Apparatus turned off immediately, experiment aborted and material made safe. | Notified to Comcare |
| 16 Jun 2010 | Staff member knocked head on overhead pipe when conducting plant inspection causing localised swelling. Signage in area improved and staff reminded of hazard. | Notified to Comcare |
| 9 Jun 2010 | Batch of imported bulk I-131 received at ANSTO Health with radioactivity in excess of ordered amount, as well as licence condition. Stored for safety until decayed to permissible level on 11 June, 2010. Supplier notified to ensure event not repeated.
| Notified to ARPANSA |
| 14 May 2010 | Small, non-exempt batch of technetium-99m incorrectly identified as being below exemption levels leading to some documentation not being fully completed. Material was handled in accordance with standard radiation protection techniques and there were no radiological consequences.
| Notified to ARPANSA |
| 3 May 2010 | A contractor received a pinch injury resulting in a laceration of his left thumb that required surgical repair. The contractor advised NSW WorkCover. | Notified to Comcare |
| 28 Apr 2010 | An electrical contractor received an electric shock from the neutral cable when a distribution board was being replaced. No medical assistance was required. Power to the board had been isolated, checked and verified by ANSTO and Contractor.
| Notified to Comcare |
| 17 mar 2010 | A precautionary notification of staff removing asbestos-containing material. Staff were not exposed to asbestos as appropriate controls were in place. During refurbishment operation in a tented enclosure with staff wearing Personal Protective Equipment, friable asbestos was dislodged. Staff collected and bagged the material, however, they did not have appropriate qualifications to remove it.
| Notified to Comcare |
| 11 mar 2010 | Contractors entered a work area with potential low-level beryllium contamination without appropriate assessment and approval. Follow-up tests showed that there was no beryllium in the area.
| Notified to Comcare |
| 11 Feb 2010 | As part of an internal audit, it was found that levels of Fluorine-18 ordered by ANSTO Life Sciences (formerly RRI) between September 2007 and February 2010 were in excess of that permitted by the licence conditions. The sources were handled in accordance with standard radioactive handling procedures and there were no safety implications of the breach.
| Notified to ARPANSA |
| 31 Jan 2010 | Radioactive medical isotope (Yttrium 90) droplet dripped on floor and on bench under fume-hood during quality control testing. Minor localised contamination to employee's lab coat and forearm which were decontaminated promptly.
| Notified to ARPANSA |
| 28 Jan 2010 | An induction heater was disposed of without prior approval from ARPANSA. As the heater was inoperable and did not contain any radioactive material, there were no safety implications.
| Notified to ARPANSA |
| 27 Jan 2010 | Ten radioactive medical isotope (Iodine-131) capsules with incorrect labelling recalled. Two had been shipped to customers. None administered to patients. Capsules had higher activity limits than required. | Notified to NGA |
| 22 Jan 2010 | As part of an internal audit, it was found that a batch of Germanium-68 was ordered by ANSTO Life Sciences (formerly RRI) in January 2008 in excess of that permitted by the licence conditions. The source was handled in accordance with standard radioactive handling procedures and there were no safety implications of the breach.
| Notified to ARPANSA |
| 21 Jan 2010 | Spill of less than 1 millilitre radioactive medical isotope (Technetium-99m) in laboratory during tests. Contamination was spread to adjacent areas of the laboratory resulting in contamination of overshoes and localised personal contamination to three employees, all of whom were decontaminated promptly. Laboratory was decontaminated and returned to service.
| Notified to ARPANSA |
| 12 Jan 2010 | Empty depleted uranium container dislodged from contractors transport vehicle when strapping broke during return to package owner. No safety consequence to public. Transport arrangements and securing mechanisms reviewed and improved. Notified to NSW EPA by external agency.
| Notified to NW EPA by external agency |
| Jan 2010 | A radioactive Caesium 134 source had higher than anticipated activity requiring temporary storage within a dedicated shielded enclosure. When packing the source elevated dose levels in the localised area were recorded and the item was returned to the shielded enclosure. No significant doses to employees were recorded. | Notified to ARPANSA |
Note: This information has been updated progressively. Historic incidents will be reviewed to ensure accurate presentation of fact.
Last updated: 2 May 2011
[back to top]
. 19 Nov 2010 A contractor received a mild electric shock when they came into contact with the metal work of the false ceiling support grid. The electrical supply was isolated, and the source of the fault was found to be a damaged power cord adjacent to the fitting that had come into contact with the false ceiling support metalwork. No injury was received from the shock. Notified to Comcare
