November 2023 – User operations underway
User operations on BioSAXS commenced on October 26th 2023 with a user group from UniSA using our Linkam stage, closely followed by a group from CSIRO utilising the Peltier capillary rack.
The Coflow unit arrived at the synchrotron and is undergoing final site acceptance testing before being integrated into the beamline
August 2023 – BioSAXS end station readiness review complete
In August 2023, the BioSAXS Pilatus 2M detector was installed in the vacuum vessel and final testing for readiness review was completed.
The first image on the BioSAXS detector was recorded on the eve of the August shutdown, ready for hot commissioning in 2023 cycle 3.
July 2023 – BioSAXS approaching user operations
Many milestones have been achieved on BioSAXS over the last 12 months, all of which has led to BioSAXS being poised to enter user operations in 2023 cycle 3.
In August 2022, the vacuum vessel that houses the BioSAXS detector was installed in the experimental hutch after passing its factory acceptance tests at the local supplier in Melbourne. Following installation works, the site acceptance tests for the vessel were completed a few weeks later, certifying the vessel ready for operations.
Shortly after this in September 2022, the superconducting undulator was installed in the synchrotron storage ring, giving the beamline its light source.
Following approval by ARPANSA to commence taking beam, first light on BioSAXS was achieved in late November 2022, about a week before the Christmas-New Year shutdown – making for an early festive gift for the project team.
In the new year, work began in earnest on hot commissioning the photon delivery system of the beamline, threading the beam through the beamline optics used to generate a focussed beam of well-defined X-ray energy.
September 2021 - Good progress on BioSAXS despite lockdown challenges
Despite the many challenges brought by the COVID-19 pandemic and subsequent lockdowns, individuals and organisations are managing to make progress on important projects.
The addition of six new beamlines as part of Project Bright at the Australian Synchrotron was impacted shortly after work had started on the many stages needed to order and install the new technology.
Lead scientist on the BioSAXS beamline, Dr Christina Kamma-Lorger remains optimistic that new instrument will be operational by the second half of next year.
An issue arose this year when chaos in the Port of Singapore impacted by the blockage in the Suez Canal, caused some early delays. The lead shielding was transported to Australia by ship from Innospec Prüfsystem GmbH (Dresden, Germany).
“The first components, protective shielding for the instrument, started arriving in mid-August. A supervising technician from the vendor who supplied them went into quarantine, while our team started assembling the structure,” said Kamma-Lorger.
Hutch A, a teal-coloured rectangular container, is now assembled with work on Hutch B underway.
“The instruments around the new beamline are very sensitive to vibrations, so that called for extra care with the positioning work,” she said.
The next step after Hutch B is assembled is the installation of utilities, possibly by late November.
Subsequent work will involve the addition of the user cabin and photon delivery system.
“The very last stage is the installation of the insertion device in the storage ring,” said Kamma-Lorger.
She added that the great effort by internal engineering, computing and technical teams, in collaboration with local and overseas vendors, has driven progress on the installation of the 40-metre beamline.
“After the instrument is commissioned next year, our users will have access to a high-flux beamline that can be used to study chemical and biological systems at the nanoscale.
“Even samples that are highly sensitive to radiation can be studied using the CoFlow sample environment developed at the Australian Synchrotron,” she added.